(name of investment project, proposal)

Tuvinian Institute of Complex Mastery of Natural Resources of the Russian Academy of Sciences. Siberian Branch

(name of enterprise (organization) - the initiator of project, proposal)

Information about the Enterprise (organization) - the initiator of the project, proposal:

Address:

177 "a", Internatsionalnaya Street, Kyzyl, the republic of Tyva, 667007

Telephone:

tel.: 8(39422)2-17-53

Fax:

8(39422)2-17-53

E-mail:

*****@***ru

Leader:

Lebedev Vladimir Ilyich - the director of TICMNR SB RAS.

Description of the production:

Business-idea, the purpose of the project:

Complex processing of the group of enterprises' waste

A brief description of the region in which the project is intended to be realized:

Barun-Khemchik district of the Republic of Tyva (Western part of the republic)

Guarantee of the project with raw materials:

Production waste of ore mining and processing enterprise «Tuvaasbest» - 80 mln. m.

Planned production (introduced power):

Design capacity of the plant: Oxide of silicon (cleanliness 99,99%) -4800kg.; Oxide of magnesium (cleanliness 99,99%) -4800kg.; gypsum - 6048kg.; ferrous product - 2016kg.

Consumers' market description:

Heat and power plant, the producers of modern semiconductor materials for the computer technology

Readiness degree and project examination:

The Business-plan, developed by Тувинским институтом комплексного освоения природных ресурсов СО РАН. Today the project on obtaining of the industrial standard of extra-pure silicon from the serpentinite waste of ore mining and processing enterprise is being realized.

Financial estimation of the project:

The total cost of project (mln. of roubles):

750 mln. roubles.

including:

-own investments

-

-the enquired investments

750 mln. roubles.

Forms of investment:

Direct investment, participation in capital, long-term crediting

Expenditures articles:

New building.

Normative period of building (project realization):

5 years

Period of the compensability:

3 years

Profitability of the project:

55,5 %

Internal rate of profitability (IRR):

61,43%

Forms of the return of the investments:

Clear profit not less than 6,7 mln. roubles.

Additional information:


Organization of the wood processing enterprise of complete technological cycle in Kyzyl

НЕ нашли? Не то? Что вы ищете?

(name of investment project, proposal)

___________________ The Government of the Republic of Tyva__________________

(name of enterprise (organization) - the initiator of project, proposal)

Information about the Enterprise (organization) - the initiator of the project, proposal:

Address:

11, Kalinina Street, Kyzyl, 667009

Telephone:

tel.(394

Fax:

8(39422)5-15-57

E-mail:

*****@***ru

Leader:

Responsible person - Sagan-ool Karim Bailak-oolovich, acting as the minister of industry and power engineering of the Republic of Tyva

Description of the production:

Business-idea, the purpose of the project:

Creation of timber complex in Kyzyl of complete closed cycle of production, from obtaining of raw material to the output of glued product and profile moulded articles.

A brief description of the region in which the project is intended to be realized:

Kyzyl, the Republic of Tyva (the capital)

Guarantee of the project with raw materials:

It is intended to supply wood from two forest resource bases: the base "Shivey" in Kaa-Khem district and the base in the natural boundary Irtysh in Tes-Khem district. Calculated annual cutting area on fellings of main use is 2,2 mln. cubic meters, including the coniferous economy -1,9 mln. cubic meters.

Planned production (introduced power):

The volume of output of lumber - 45 thousand cubic meters per annum.

Consumers' market description:

It is oriented predominantly for the domestic market.

Readiness degree and project examination:

Investment proposal (idea); there are no technical and economic assessment, design estimates.

Financial estimation of the project:

The total cost of project (mln. of roubles):

340 mln. roubles.

including:

-own investments

-

-the enquired investments

340 mln. roubles.

Forms of investment:

Direct investment, participation in capital

Expenditures articles:

New building

Normative period of building (project realization):

2 years

Period of the compensability:

5 years

Profitability of the project:

24%

Internal rate of profitability (IRR):

37,54%

Forms of the return of the investments:

Clear profit - 65,1 mln. roubles per annum

Additional information:

Tax revenues will be about 49,0 mln. roubles. Number of personnel -121 people.

The expected portion of new enterprise in the carrying out of production of timber complex will be 60%.


Building of the waterpower station with the power of 1500 MW., power transmission line from waterpower
________________________________________ station________________________________________

(name of investment project, proposal)

__________________________ The Government of the Republic of Tyva__________________________

(name of enterprise (organization) - the initiator of project, proposal)

Information about the Enterprise (organization) - the initiator of the project, proposal:

Address:

18, Chuldum Street, Kyzyl, the Republic of Tyva

Telephone:

tel.: 8(394, 3-25-56

Fax:

8(39422)2-16-56

E-mail:

mineconom(a)*****

Leader:

Responsible person - Oyun Buyan Dadyi-oolovich, the deputy minister for economy of the Republic of Tyva

Description of the production:

Business-idea, the purpose of the project:

Guarantee of realization of the "Aluminum plant building on the base of Bayan-Kol deposit" project, the satisfaction of the increasing consumption of electric power in the republic, the creation of infrastructure for the realization of major investment projects.

A brief description of the region in which the project is intended to be realized:

Todzha district, the Republic of Tyva (North-Eastern direction of the republic).

Guarantee of the project with raw materials:

The Yenisey

Planned production (introduced power):

1500 M W of the electrical energy

Consumers' market description:

Aluminum plant on the base of Bayan-Kol deposit, companies-investors that realize major investment projects (Kyzyl-Kuragino railway building, the mastery of the Kyzyl-Tashtyg polymetallic, Ak-Sug copper-porphyritic deposits, and Elegest and Mezhegey coal-fields).

Readiness degree and project examination:

Investment proposal (idea); there are no technical and economic assessment, design estimates.

Financial estimation of the project:

The total cost of project (mln. of roubles):

75 000 (additionalmln. roubles for power transmission line)

including:

-own investments

-

-the enquired investments

75 000 (additionalmln. roubles for power transmission line)

Forms of investment:

Direct investment

Expenditures articles:

New building

Normative period of building (project realization):

5 years (power transmission line from the waterpower station - 3 years)

Period of the compensability:

12 years

Profitability of the project:

18%

Internal rate of profitability (IRR):

18,6%

Forms of the return of the investments:

Clear profit about 4,5 mln. roubles per annum

Additional information:

Index of profitability - 1,03

Clear given income NPV -mln. roubles